HyNet: CO2 storage advances while hydrogen stalls
Liverpool Bay storage has financial close, but Cadent's hydrogen pipeline consent is paused and a gas-plant project lost priority status.
HyNet North West is advancing unevenly: carbon storage in Liverpool Bay has reached financial close, but hydrogen has stalled. Cadent has paused its pipeline consent order, the first Stanlow hydrogen plant still awaits financial close, and Connah's Quay was reported dropped from the priority list in November 2026.
The Gulf Barrel Desk · 3 min read- Confirmed: DESNZ and Eni reached financial close on the Liverpool Bay carbon storage project in April 2025, per Energy Voice.
- Reported: Cadent has paused its development consent order for the hydrogen pipeline because the hydrogen transport business model is delayed.
- Unconfirmed: the first 350 MW Stanlow hydrogen plant still awaits financial close, with a decision only targeted by the end of 2026.
- Reported: DESNZ moved Uniper's Connah's Quay gas plant off the priority list in November 2026, and Uniper says it needs time to assess the effect.
- The sources give no HyNet-specific share of the £21.7 billion Track-1 programme, no total capital cost and no new consent date.
HyNet North West's carbon storage is further along than its hydrogen. As of 22 November 2026, Energy Voice reports that the Liverpool Bay storage project has reached financial close, while the hydrogen pipeline consent is paused and a major gas-plant capture project has lost priority status. Neither Energy Voice nor HyNet's own pages put a cost or new timetable on the delays. This is analysis, not advice.
What is confirmed: the storage backbone
The confirmed part of HyNet is transport and storage. Energy Voice reports that DESNZ and Eni reached financial close on the Liverpool Bay carbon project in April 2025, with CO2 headed for the depleted Hamilton, Hamilton North and Lennox fields through a main onshore pipeline of roughly 60 km. That is the piece with a funded commitment behind it. The rest of the cluster depends on emitters and hydrogen producers actually connecting to it.
Hydrogen is where the timetable slips
Hydrogen is slipping because the commercial framework is late. Energy Voice reports Cadent has paused its development consent order for the planned 100 to 125 km hydrogen pipeline, citing the delayed hydrogen transport business model that government had aimed to finalise in spring 2026. The first 350 MW blue hydrogen plant at the Stanlow refinery still awaits financial close, with a final investment decision only targeted by the end of 2026. That target is unconfirmed.
Connah's Quay is the clearest recent setback
Connah's Quay is the clearest recent setback. Energy Voice reports DESNZ moved the 1.38 GW Uniper gas plant, which would capture about 3.7 million tonnes of CO2 a year, off the priority list in November 2026. Uniper said it would take time to assess the implications, and the energy secretary's decision on its consent order is pending. Other emitters continue: Padeswood took a final investment decision in September 2025 and targets operations in 2029.
What the sources do not say
The sources are silent on several key numbers. Neither the Energy Voice guide nor HyNet's own pages state HyNet's individual share of the £21.7 billion Track-1 programme, its total capital cost, or a new date for the Cadent consent order. HyNet's website claims a quarter cut in regional CO2 and 2,000 jobs, while the guide cites an aim to capture up to 95% of regional emissions. Neither source reconciles the two framings.
- What part of HyNet North West is actually funded and committed?
- Energy Voice reports that DESNZ and Eni reached financial close on the Liverpool Bay carbon transport and storage project in April 2025. That is the clearest committed element. The hydrogen production and pipeline elements have not reached the same stage.
- Why has the HyNet hydrogen pipeline slipped?
- Energy Voice reports that Cadent paused its development consent order because the hydrogen transport business model has been delayed. Government had planned to finalise that framework in spring 2026. The guide gives no new date.
- Does the Connah's Quay setback end the project?
- Not on the evidence available. Energy Voice reports DESNZ moved it off the priority list in November 2026 and that Uniper is assessing the implications. The energy secretary's decision on its consent order is still pending, so its fate is unresolved.
- A guide to HyNet North West Hydrogen and CCS cluster — Energy Voice
- HyNet: the UK's leading industrial decarbonisation project — HyNet North West
- HyNet partners and funding — HyNet North West