Sasol and ENH Study a Floating LNG Terminal in Mozambique
Sasol and ENH signed an MoU to study a floating LNG terminal in southern Mozambique. It is a feasibility step, with no investment decision.
Sasol and ENH have signed a memorandum of understanding to study a floating LNG import terminal in southern Mozambique, but it commits neither party to build anything. The agreement is a feasibility step, not an investment decision, and its value depends on gas supply still years away.
The Gulf Barrel Desk · 3 min read- Sasol and ENH signed a memorandum of understanding to assess an FSRU-based LNG terminal in southern Mozambique, according to LNG Prime.
- An MoU is a study commitment, not a final investment decision, and no cost or schedule has been confirmed for the terminal itself.
- Reuters reported in October 2026 that ENH was discussing a roughly $250 million project with Sasol and ROMPCO, with infrastructure targeted for around 2030 or 2031.
- The project is aimed at replacing declining southern Mozambique pipeline gas that feeds South African industry.
- This is analysis, not trading or investment advice.
Sasol, the South African petrochemicals group, and ENH, Mozambique's state oil and gas company, have signed a memorandum of understanding to assess an FSRU-based LNG terminal in southern Mozambique, according to LNG Prime. The document is a feasibility agreement. It does not authorise construction, fix a budget or secure LNG supply, and the desk has not seen its text. What matters is the problem it points at: South African industry's dependence on declining pipeline gas.
What the memorandum does and does not do
The memorandum commits the two companies to study whether a floating storage and regasification unit off southern Mozambique is workable. It is not a final investment decision, and neither party has published a cost, a capacity or a start date for the terminal itself. Sasol said earlier that it was analysing options to guarantee its supply needs but that it was too early to define an investment, as reported by Engineering News.
The gas gap behind the deal
The driver is supply decline rather than demand growth. Engineering News reported in 2024 that Sasol and Eskom were exploring LNG imports to replace falling gas from southern Mozambique, with the Matola LNG project near Maputo still short of a final investment decision. An import terminal would add a second route for gas to reach South African users. That route would be set by what Sasol can contract and at what delivered price, which no source has disclosed.
The reported $250 million concept
Reuters, via Engineering News, reported in October 2026 that ENH was in talks with Sasol and ROMPCO on a project of about $250 million, centred on Beira and Inhassoro. It would involve floating units at both locations. ENH's chief executive tied the timeline to the northern Mozambique LNG projects, targeting infrastructure around 2030 or 2031. That figure and schedule are reported estimates, not confirmed terms of this memorandum.
What to watch next
The key test is whether a feasibility study leads to a named LNG supplier and a delivered-price indication. Without contracted cargoes from the Afungi projects or other sources, a regasification vessel is only a berth. Watch for any disclosed supply agreement, a cost estimate from Sasol or ENH, and any regulatory step in Mozambique. This is analysis, not trading or investment advice.
- What did Sasol and ENH sign?
- They signed a memorandum of understanding to assess the feasibility of an FSRU-based LNG terminal in southern Mozambique, as reported by LNG Prime. It is a study agreement, not a construction or investment commitment.
- Why does southern Mozambique need an LNG terminal?
- Sasol has said it is analysing options to secure its gas supply. Earlier reporting links the idea to declining gas from southern Mozambique and to feeding LNG into the ROMPCO pipeline system.
- Is the terminal approved or funded?
- No. Reuters, via Engineering News, reported that Sasol considered it too early to define a possible investment in the ENH project. The reported cost of about $250 million is an estimate.
- Sasol, ENH ink LNG terminal MoU — LNG Prime
- Mozambique courts South African investment for new gas project — Engineering News
- Sasol and Eskom to explore demand anchors for LNG as part of effort to avert 'gas cliff' — Engineering News