Humber CCS Needs a Second Pipeline and a Funding Model
The Humber Energy Board's Iain Harris says the region needs two CCS pipelines, but government funding signals have tightened.
The Humber's CCS case is a funding problem more than a pipe problem. Iain Harris of the Humber Energy Board says the region needs two pipelines, but only one has planning approval, and government has signalled no repeat of the £21.7 billion Track-1 funding. Viking CCS targets a final investment decision by 2029. This is analysis, not advice.
The Gulf Barrel Desk · 3 min read- Iain Harris, managing director of the Humber Energy Board, said the region has always needed at least two CCS pipelines; only one currently has planning approval, as reported by Energy Voice on 20 November 2026.
- Harris cited around 20 million tonnes a year of CO2 emitted in the Humber, which he described as the UK's largest emitting area, per Energy Voice.
- Track-1 projects received £21.7 billion of government funding over 25 years; Harris said October budget signals point to no repeat for further CCS.
- The 'more difficult playing field' is Harris's description of the government's move away from funding everything, with loans or equity signalled but unexplained.
- Harbour Energy's 2022 consultation notice described a 55 km onshore line from Immingham to Theddlethorpe; its timings are three years old. This is analysis, not advice.
Energy Voice reported on 20 November 2026 that Iain Harris, managing director of the Humber Energy Board, wants a second carbon capture pipeline for the Humber. The sharper story is who pays. Harris said the government has moved away from funding everything, and that makes the field harder. This is analysis of that reporting, not advice, and every figure below is attributed to its source.
Why two pipelines, according to Harris
Speaking in Hull, Harris said the region has always needed at least two CCS pipelines to decarbonise, and that only one currently has planning approval. Energy Voice quotes him citing around 20 million tonnes a year of CO2 in the Humber, which he called the UK's largest emitting area, and 66% of UK licensed CO2 storage lying just offshore. These are his assertions as reported, not independently verified figures.
What the 'more difficult playing field' means
The phrase is Harris's reading of the government's clarified position on CCS and hydrogen funding. Energy Voice reports he said some projects will be very disappointed, and that it makes for a more difficult playing field. Track-1 projects received £21.7 billion over 25 years, and Harris said the October budget and political signalling suggest that will not be repeated for further CCS.
Loans and equity are signalled, not defined
According to Energy Voice, the government has shown interest in loans or equity instead of grant-style support, but Harris asked how those would work. He said the industry needs a clear business model, a clear structure and the cluster. The article does not set out the mechanics, so the desk cannot assess how a loan or equity model would change returns or risk for a Humber project.
Where Viking CCS and the first pipeline stand
Energy Voice reports Harris welcomed budget support for Viking CCS, which aims for a final investment decision during this parliament, by 2029. The Northern Endurance Partnership consulted on its Humber pipeline in the summer, with a consent application planned for early 2027 and construction from 2029, running from Drax to near Easington. Harbour Energy's November 2022 notice described a 55 km onshore line from Immingham to Theddlethorpe; its 2025 construction target is now outdated.
What to watch next
Three things decide whether a second Humber pipeline is financeable: published terms for any government loan or equity route, the early-2027 consent submission for the Humber pipeline, and an updated Viking CCS timetable from Harbour Energy. Until those appear, the argument for two pipelines is a regional industry position about demand and storage, not a funded programme. Nothing here is a call on any project or security.
- Why does the Humber Energy Board say the Humber needs its own CCS pipeline?
- Iain Harris said the region has always needed at least two CCS pipelines, and only one has planning approval. He pointed to roughly 20 million tonnes a year of CO2 emissions in the area, as reported by Energy Voice.
- What is the 'more difficult playing field'?
- Harris used the phrase for the government's clarified stance that it will not fund everything. Energy Voice reports ministers have signalled interest in loans or equity, and Harris asked how those would work.
- What is the status of Viking CCS?
- Energy Voice reports Harris welcomed budget support for Viking CCS, which aims for a final investment decision during this parliament, by 2029. Harbour Energy's 2022 notice, now dated, targeted construction from 2025.
- Is this investment advice?
- No. This is analysis of public reporting on infrastructure policy, not a trading call or investment recommendation.
- Humber needs its own CCS pipeline — Energy Voice
- Viking CCS pipeline progresses towards DCO with statutory consultation — Harbour Energy