HyNet's CCS Build Advances, Hydrogen Side Still Stuck

HyNet's CCS Build Advances, Hydrogen Side Still Stuck

HyNet's CO2 storage is financed, but hydrogen lacks a final investment decision and pipeline model. Capture targets remain unproven.

HyNet's carbon-capture build-out is advancing but remains conditional: the hydrogen half still lacks a final investment decision and a government transport business model. Uniper's Connah's Quay plant was moved off the priority list in November 2026. Reported capture targets are ambitions, not delivered tonnes, and this is analysis, not advice.

The Gulf Barrel Desk · 4 min read

HyNet, the North West England and North Wales carbon-capture and hydrogen cluster, has its CO2 storage financed but not its hydrogen supply chain. Energy Voice's November 2026 guide shows capture projects moving at different speeds, with one major gas plant dropped from the priority list. The headline tonnage figures are targets, not measured volumes, and the data is silent on a cluster-wide total.

What is confirmed

Confirmed: HyNet was named one of the government's Track 1 clusters, sharing a £21.7 billion programme with Teesside and the Humber, according to Energy Voice. DESNZ and Eni reached financial close on the Liverpool Bay CCS project in April 2025, which Energy Voice describes as the signal that construction could begin. The main onshore CO2 pipeline is about 60 km. These are the load-bearing facts; most else in the cluster is a target rather than a finished asset.

Where the hydrogen side is stuck

The hydrogen half is not yet financed. Energy Voice reports the 350 MW Stanlow plant, run by EET, still awaits financial close, with a decision targeted by the end of 2026, while Cadent has paused its development consent application for the hydrogen pipeline because the government's hydrogen transport business model is delayed. Officials had planned to finalise that model in spring 2026. Until it lands, hydrogen volumes and offtake for Pilkington UK and Encirc remain plans, not flows.

Capture targets and the Uniper setback

Capture projects carry the largest tonnage claims, and the largest uncertainty. Energy Voice reports Uniper's 1.38 GW Connah's Quay plant, aimed at about 3.7 million tonnes a year, was moved off the priority list in November 2026, and Uniper said it would take time to understand the implications. By contrast, Heidelberg Materials took a final investment decision at Padeswood in September 2025, for roughly 800,000 tonnes a year.

Sources disagree on storage

The two sources describe hydrogen storage differently. Energy Voice names Storengy UK's Keuper project, up to 1,300 GWh in as many as 19 Cheshire salt caverns, while HyNet's own About page names INEOS Inovyn repurposing caverns near Northwich for 35,000 tonnes. They may be related, but the units differ and neither source reconciles them, so the scale is unverified. HyNet's homepage also cites 2,000 jobs, attributed only to an energy secretary and undated.

What to watch next

Three markers will show whether the hydrogen side catches up with storage: a Stanlow financial close by the end of 2026, publication of the government's hydrogen transport business model, and DESNZ's next step for Connah's Quay. A slip in any of them would put hydrogen timelines under pressure against the 2029 and 2030 dates quoted for capture projects. Nothing here is a view on prices or a trading call; it is analysis, not advice.

Is HyNet's carbon capture actually funded?
The Liverpool Bay CO2 transport and storage project reached financial close with DESNZ and Eni in April 2025, per Energy Voice. Individual emitter projects vary: Padeswood took a final investment decision in September 2025, while others remain targets.
What is holding up HyNet's hydrogen side?
Energy Voice reports the Stanlow plant awaits financial close and Cadent has paused its pipeline consent application because the government's hydrogen transport business model is delayed.
Do the sources agree on hydrogen storage?
No. Energy Voice names Storengy UK's Keuper project at up to 1,300 GWh, while HyNet's About page names INEOS Inovyn and 35,000 tonnes. The two may be related, but neither source reconciles them.